Start of Final Commissioning Test at Reprocessing Plant
(March 31, 2006)
|
|
"Final Commissioning Test" is the final confirmation test of
the Reprocessing Plant, using actual nuclear spent fuel, which follows
"Joint Test" , "Chemical Test" and "Uranium Test",
already successfully performed.
(1) |
Joint Test : Confirmation of the joints of tanks and pipes, etc.(use water,
air etc.)
|
(2) |
Chemical Test : Confirmation of the suitability of machines and equipments
for acid solvent and organic solvent.
|
(3) |
Uranium Test : Confirmation of the suitability of the machines and equipments
for the uranium.(use depleted uranium.)
|
|
|
|
|
|
|
|