JAPAN NUCLEAR FUEL LIMITED

May 27 1997

Press Release Concerning Receipt of Fifth Authorization for Reprocessing Facility Design and Construction


Japan Nuclear Fuel Limited


JNFL announced that in response to its application dated February 28 1996, it today received the fifth authorization for reprocessing facility design and construction from the director of the Science and Technology Agency. Following are the main items of equipment in the Head End Building for which the design and construction were approved today.


1.

Main Reprocessing System

*

Shearing machines which shear spent fuel assemblies received from the fuel supply equipment

*

Dissolving equipment used to dissolve sheared fuel pieces in nitric acid after they are received from the shearing machines


2.

Measurement and Control Systems

*

Measurement and control equipment necessary for safe operation and control of shearing machines and dissolvers

*

Safety monitoring equipment which detects criticality in the shearing machines and restores them to their normal state


3.

Disposal Systems

*

NOx scrubbing column, iodine desorption column, blowers, etc. in the Shearing Off Gas and Dissolution Off Gas Treatment Sub-Facility, to treat radioactive gaseous waste produced during the shearing and dissolving processes

*

Portions of the Vessel Off Gas Treatment Sub-Facility which treat radioactive gaseous waste contained radioactive materials in Head End Building

*

Ventilation equipment including ventilators, exhaust fans, etc.


[ Reference]

Chronology of Applications and Authorizations for Reprocessing Facility Design and Construction

1992

December 24

Reprocessing facility operator approval granted


1993

January 13

First design and construction application files

April 14

First approval granted

April 28

Construction of the reprocessing plant begins

July 30

Second design and construction application filed

December 27

Second approval granted


1994

April 12

Third design and construction application filed

July 22

Third approval granted

October 21

First modification of design and construction application filed

November 25

First modification approval granted


1995

April 18

Second modification of design and construction application filed

April 28

Second modification approval granted

May 22

Fourth design and construction application filed

September 26

Fourth approval granted


1996

February 28

Fifth design and construction application filed

August 8

Third modification of design and construction application filed

September 20

Third modification approval granted