JAPAN NUCLEAR FUEL LIMITED

June 17 1997
Press Release Concerning the Start of Test Operations at the RE-2A Production Facility at the Rokkasho Uranium Enrichment Plant Scheduled for FY1997

Japan Nuclear Fuel Limited

JNFL currently operates the RE-1 (600tSWU/a) production facility which was built during the first phase of construction at the Rokkasho Uranium Enrichment Plant. Construction work on the first half of the RE-2 (450tSWU/a) production facility which was begun in September 1993 is now complete, and test operation of RE-2A (150tSWU/a) is scheduled to begin on 18 June 1997. Full-scale operations are expected to begin in October 1997.
[Reference]
In test operations, uranium hexafluoride (UF6) will undergo treatment, homogenization & blending operations, after which the equipment used will be thoroughly inspected. The UF6 will then be placed into a centrifuge for final processing. After confirming that enriched uranium can be produced, integrated production capacity (150tSWU/a) will be checked.
Testing Procedures
1. A feed cylinder will be inserted in the feed cylinder vessel to produce UF6.

2. The function of homogenization equipment will be tested by processing UF6 in a homogenization vessel. Prior to the cascade process, the condition of all pre-treatment equipment will be examined.

3. Production capacity will be tested by placing UF6 gradually into cascade equipment while checking the state of the centrifuges.

Chronology of Rokkasho Uranium Enrichment Plant Operations to Date

Phase I (RE-1 [600tSWU/a])
1987 May Application to operate nuclear fuel manufacturing business filed
1988 August Permission to operate nuclear fuel manufacturing business granted
October Construction of RE-1 uranium enrichment plant begins
1992 March Operations at RE-1A (150tSWU/a) begin
December Operations at RE-1B (150tSWU/a) begin
1993 May Operations at RE-1D (150tSWU/a) begin
1994 September Operations at RE-1C (150tSWU/a) begin
Phase II (Stage 1 of RE-2 [450tSWU/a])
1992 July Application to expand nuclear fuel manufacturing business filed
1993 July Permission granted
September Construction of RE-2 uranium enrichment plant begins
1997 October Operations at RE-2A (150tSWU/a) scheduled to begin