JAPAN NUCLEAR FUEL LIMITED

June 20 1997

Press Release Concerning Reprocessing Facility Design and Construction Modification Application


Japan Nuclear Fuel Limited


JNFL announced that it filed an application to modify the design and construction of its reprocessing facility with the director general of the Science and Technology Agency today.


The reason for the modifications is to improve maintenance procedures for structures and facilities at reprocessing plants which have already been approved. Modifications will be reflected in design drawings for the plants. Primary modifications relate to the following:


(1) Modifications to the size and location of doors and walls in the Head End Building.


(2) Modifications to the positioning of rooms around the laundry area in the Access Control Building.


[ Reference]

Chronology of Applications and Authorizations for Reprocessing Facility Design and Construction

1992

December 24

Reprocessing facility operator approval granted


1993

January 13

First design and construction application files

April 14

First approval granted

April 28

Construction of the reprocessing plant begins

July 30

Second design and construction application filed

December 27

Second approval granted


1994

April 12

Third design and construction application filed

July 22

Third approval granted

October 21

First modification of design and construction application filed

November 25

First modification approval granted


1995

April 18

Second modification of design and construction application filed

April 28

Second modification approval granted

May 22

Fourth design and construction application filed

September 26

Fourth approval granted


1996

February 28

Fifth design and construction application filed

August 8

Third modification of design and construction application filed

September 20

Third modification approval granted


1997

May 27

Fifth approval granted