1992
|
December 24
|
Reprocessing facility operator approval granted
|
|
1993
|
January 13
|
First design and construction application files
|
April 14
|
First approval granted
|
April 28
|
Construction of the reprocessing plant begins
|
July 30
|
Second design and construction application filed
|
December 27
|
Second approval granted
|
|
1994
|
April 12
|
Third design and construction application filed
|
July 22
|
Third approval granted
|
October 21
|
First modification of design and construction
application filed
|
November 25
|
First modification approval granted
|
|
|
1995
|
April 18
|
Second modification of design and construction
application filed
|
April 28
|
Second modification approval granted
|
May 22
|
Fourth design and construction application filed
|
September 28
|
Fourth approval granted
|
|
1996
|
February 28
|
Fifth design and construction application filed
|
April 28
|
Reprocessing business modification application
filed
|
August 8
|
Third modification of design and construction
application filed
|
September 20
|
Third modification approval granted
|
|
1997
|
May 27
|
Fifth approval granted
|
June 20
|
Fourth modification of design and construction
application filed
|
July 23
|
Fourth modification approval granted
|
July 29
|
Reprocessing business modification granted
|
August 8
|
Fifth modification of design and construction
application filed
|
September 10
|
Fifth modification approval granted
|
September 22
|
Sixth design and construction application filed
|
|
1998
|
February 27
|
Sixth modification of design and construction
application filed
|