April 1 1998

Press Release Concerning the Start of Full-Scale Operations at the RE-2B Production Facility at the Rokkasho Uranium Enrichment Plant Scheduled for FY1998


Japan Nuclear Fuel Limited


JNFL announced that test operations at RE-2B (150tSWU/a) which were begun on 9 January 1998 have been completed, and that full-scale operations were started today.

With the start of full-scale operations at RE-2B (150tSWU/a), capacity at the Rokkasho Uranium Enrichment Plant, including the already operating RE-1(600tSWU/a) and RE-2A (150tSWU/a) will be 900 tons SWU annually.


[Reference]

Chronology of Rokkasho Uranium Enrichment Plant Operations to Date


Phase I (RE-1 [600tSWU/a])

1987

May

Application to operate nuclear fuel manufacturing business filed

1988

August

Permission to operate nuclear fuel manufacturing business granted

October

Construction of RE-1 uranium enrichment plant begins

1992

March

Operations at RE-1A (150tSWU/a) begin

December

Operations at RE-1B (150tSWU/a) begin

1993

May

Operations at RE-1D (150tSWU/a) begin

1994

September

Operations at RE-1C (150tSWU/a) begin

Phase II (Stage 1 of RE-2 [450tSWU/a])

1992

July

Application to expand nuclear fuel manufacturing business filed

1993

July

Permission granted

September

Construction of RE-2 uranium enrichment plant begins

1997

October

Operations at RE-2A (150tSWU/a) begin

1998

April

Operations at RE-2B(150tSWU/a) scheduled to begin

October

Operations at RE-2C(150tSWU/a) scheduled to begin